ELECTRIC

EL03-019 In the Matter of the Filing by Montana-Dakota Utilities Co. for Approval of Tariff Revisions.

Application by Montana-Dakota Utilities Co. for approval to update Occasional Power Purchase Non-Time Differentiated Rate 95, Short-Term Power Purchase Time Differentiated Rate 96 and Long-Term Power Purchase Time Differentiated Rate 97. Pursuant to Commission Order and tariffed terms and conditions, these rates are reviewed annually and revised when necessary. The rates proposed were developed using the same methodology as was used for the rates currently on file.

Staff Analyst: Dave Jacobson
Staff Attorney: Karen Cremer
Date Docketed: 06/03/03
Intervention Deadline: 06/20/03

EL03-020 In the Matter of the Filing by Xcel Energy for Approval of the Inclusion of Financial Incentives in its Fuel Clause.

Application by Xcel Energy (Xcel) for approval to continue flowing the costs and effects of its hedging transactions for years 2002 and 2003 through its fuel clause pursuant to the terms and conditions ordered in Docket EL99-021. The Commission's decision in Docket EL99-021 approved Xcel's proposal to flow the costs and effects of hedging transactions through Xcel's fuel clause with conditions, including recurring annual approval and biannual reporting requirements. Xcel neglected to obtain approval to continue inclusion of its hedging activity in its fuel clause for the year 2002 and now requests that approval and also approval for 2003. Xcel is also requesting that the reporting requirement be revised to now be annual instead of biannual.

Staff Analyst: Dave Jacobson
Staff Attorney: Kelly Frazier
Date Docketed: 06/03/03
Intervention Deadline: 06/20/03

TELECOMMUNICATIONS

TC03-090 In the Matter of the Filing for Approval of an Amendment to an Interconnection Agreement between Qwest Corporation and Midcontinent Communications.

On May 30, 2003, the Commission received a Filing of End Office with Local Tandem Functionality Amendment to Agreement between Qwest Corporation (Qwest) and Midcontinent Communications (f/k/a Midco Communications "Midco"). According to the parties, the Amendment is an amendment to the negotiated agreement reached between the parties which was approved by the Commission effective May 5, 1999, in Docket TC99-023. The amendment is made in order to add End Office with Local Tandem Functionality language to the Agreement, stating that to the extent Qwest is using a specific end office to deliver limited tandem switching functionality to itself, a wireless service provider, another CLEC, or another ILEC, it will arrange the same trunking for the CLEC. Any party wishing to comment on the agreement may do so by filing written comments with the Commission and the parties to the agreement no later than June 19, 2003. Parties to the agreement may file written responses to the comments no later than twenty days after the service of the initial comments.

Staff Attorney: Kelly Frazier
Date Docketed: 05/30/03
Initial Comments Due: 06/19/03

You may receive this listing and other PUC publications via our Web site or via internet e-mail.
You may subscribe or unsubscribe to the PUC mailing lists at http://www.puc.sd.gov